Analysis/Techno-economic analysis
Techno-economic analysis
Take an equipment list to a minimum selling price: purchased cost, the DOE/NETL capital ladder, operating cost and a discounted cash flow, with every step of the working shown.
Start
Or drop a .json file here. Files saved from this page and from the teakit desktop app both open. The file is read in your browser and never uploaded.
Inputs
Results update as you type. Each group shows its total on the right; open the ones you want to change.
01Product and plant
02Equipment
Catalogue items are priced from the 42 DOE/NETL-2002/1169 correlations (1998 US Gulf Coast, carbon steel) and escalated by CEPCI. Anything the catalogue cannot price, such as electrolyser stacks or a licensed reactor, goes in as a quoted price.
03Installation and capital
04Operating cost
05Byproducts and government credits
06Finance and method
- Correlations are carbon steel at their stated design conditions; alloy factors are applied, pressure corrections are not.
- Capital from 1998 correlations is at best AACE Class 4 (−15 to −30 % low, +20 to +50 % high) and nearer Class 5 once 27 years of escalation are counted.
- nth-plant economics: no first-of-a-kind premium. For a first commercial unit the result is a floor.
- Byproducts are credited at the price entered. Government credits are per unit produced; eligibility rules are yours to check.
Flowsheet of the calculation
Where the money goes, left to right: capital in teal, operating cost in cider, credits in olive and aqua. The numbers are this study's.
Summary of results
The same study, four costing methods
Read before quoting
Prepared figures
Drawn from the inputs above and redrawn when they change. The data behind every figure is a click away, and downloads as CSV.
Build your own figure
Pick the data, the chart and up to four series. Give it your own title, then download it as SVG for a report or as CSV for a spreadsheet.
Your own sensitivity study
Choose the inputs to move, how far down and up, and what to watch. A tornado ranks them; a spider plot shows how each one bends the answer across its range.
Cash flow, year by year
After-tax equity cash flow at the solved price, in millions of dollars.
Method and sources
The calculation follows the U.S. national-lab conventions, in order. Equipment is priced from power-law correlations, C = Cb(S/Sb)n, escalated by the Chemical Engineering Plant Cost Index and multiplied by a material factor and a location factor. Purchased cost becomes installed cost with the DOE/NETL distributive factors, a Lang factor or your own factor, and installed cost climbs the NETL ladder: bare erected cost, EPC cost, total plant cost, total overnight cost and total as-spent capital.
The headline number is the price that makes the after-tax net present value zero at your discount rate, the way NREL reports a minimum selling price. The fixed-charge-rate, capital-recovery and straight-line methods run on the same inputs beside it, because the spread between them is the quickest check that the financing assumptions are doing what you think.
Three things are easy to get wrong and are handled here: land is in the overnight cost but is never depreciated; a nominal discount rate is only paired with inflating costs; and debt drawn during construction accrues interest until start-up. The lesson explains each of them.
- NETL (2021). Cost Estimation Methodology for NETL Assessments of Power Plant Performance, NETL-PUB-22580. PDF
- Loh, H.P., Lyons, J. and White, C.W. (2002). Process Equipment Cost Estimation, Final Report, DOE/NETL-2002/1169. OSTI
- Humbird, D. et al. (2011). Process Design and Economics for Biochemical Conversion of Lignocellulosic Biomass to Ethanol, NREL/TP-5100-47764. OSTI
- Turton, R. et al. Analysis, Synthesis and Design of Chemical Processes, chapter 8 (operating labour and cost of manufacture).
- Peters, M.S., Timmerhaus, K.D. and West, R.E. Plant Design and Economics for Chemical Engineers, 5th ed., chapter 6.
- IRS Publication 946, Table A-1 (MACRS depreciation). AACE International RP 18R-97 and 16R-90 (estimate classes and contingency).